form_8k.htm
UNITED STATES
SECURITIES AND EXCHANGE COMMISSION
WASHINGTON, D.C. 20549
FORM 8-K
CURRENT REPORT
PURSUANT TO SECTION 13 OR 15(d) OF
THE SECURITIES EXCHANGE ACT OF 1934
Date of report (Date of earliest event reported): October 9, 2009
(Exact name of registrant as specified in its charter)
Delaware |
|
1-7677 |
|
73-1015226 |
(State or other jurisdiction
of incorporation) |
|
(Commission File
Number) |
|
(IRS Employer
Identification No.) |
|
|
|
|
|
16 South Pennsylvania Avenue, Oklahoma City, Oklahoma
(Address of principal executive offices) |
|
73107
(Zip Code) |
|
|
|
|
|
Registrant's telephone number, including area code (405) 235-4546
(Former name or former address, if changed since last report)
Check the appropriate box below if the Form 8-K filing is intended to simultaneously satisfy the filing obligation of the registrant under any of the following provisions (see General Instruction A.2. below):
|
|
Written communications pursuant to Rule 425 under the Securities Act (17 CFR 230.425) |
|
o |
Soliciting material pursuant to Rule 14a-12 under the Exchange Act (17 CFR 240.14a-12) |
|
o |
Pre-commencement communications pursuant to Rule 14d-2(b) under the Exchange Act (17 CFR 240.14d-2(b)) |
|
|
Pre-commencement communications pursuant to Rule 13e-4(c) under the Exchange Act (17 CFR 240.13e-4(c)) |
Section 8 – Other Events
Item 8.01. Other Events
On October 9, 2009, LSB Industries, Inc. (the “Company”) issued a press release announcing that, due to required plant adjustments, the Company anticipates that the start-up of production of urea ammonium nitrate at its facility located in Pryor, Oklahoma, will be delayed until November 2009, barring unforeseen circumstances.
The press release is attached as exhibit 99.1 to this report and is incorporated herein by reference.
|
Section 9 – Financial Statements and Exhibits |
|
Item 9.01. Financial Statements and Exhibits |
(d) Exhibits.
Exhibit Description
;
99.1 |
Press Release, issued October 9, 2009. |
SIGNATURES
Pursuant to the requirements of the Securities Exchange Act of 1934, the Company has duly caused this report to be signed on its behalf by the undersigned hereunto duly authorized.
Dated: October 9, 2009
LSB INDUSTRIES, INC.
By: /s/Tony M. Shelby
Name: Tony M. Shelby
Title: Executive Vice President and
Chief Financial Officer
ex_991.htm
LSB CONTACT: |
Investor Relations Contact: |
Tony M. Shelby, Chief Financial Officer |
Linda Latman (212) 836-9609 |
(405) 235-4546 |
Lena Cati (212) 836-9611 |
FOR IMMEDIATE RELEASE
LSB INDUSTRIES’ SUBSIDIARY EXPERIENCING
CHEMICAL PLANT START-UP DELAY
Oklahoma City, OK - October 9, 2009 - LSB Industries, Inc. (LSB) (NYSE: LXU), announced today that it has experienced certain start-up delays at the Pryor Chemical Company (PCC) subsidiary’s urea ammonium nitrate (UAN) production facility located in Pryor, Oklahoma
(Pryor Plant). LSB had previously announced that the Pryor Plant would probably be producing and shipping UAN in September 2009. Based upon the estimated time to make required plant adjustments, it is now anticipated that production at the Pryor Plant will begin in November 2009, barring unforeseen circumstances. PCC will continue to expense start-up costs until the Pryor Plant is in production.
Jack E. Golsen, LSB’s Board Chairman and CEO, stated that, “Although we have experienced a temporary delay in the start-up of the Pryor Plant, we continue to be optimistic about the prospects of this operation.”
About LSB Industries, Inc:
LSB is a manufacturing, marketing and engineering company. LSB’s principal business activities consist of the manufacture and sale of commercial and residential climate control products, such as geothermal and water source heat pumps, hydronic fan coils, large custom air handlers, the manufacture and sale of chemical products
for the mining, agricultural and industrial markets, and the provision of specialized engineering services and other activities.
This press release contains certain “forward-looking statements” which are based largely on the LSB’s expectations and are subject to various business risks and uncertainties, certain of which are beyond LSB’s control. Forward-looking statements include, but are not limited to: the
Pryor Plant will begin production in November 2009, temporary delay in the start-up of the Pryor Plant, and continuing expense of start-up cost and optimistic about the prospects of this operation. These forward-looking statements are intended to qualify for the safe harbors from liability established by the Private Securities Litigation Reform Act of 1995. While LSB believes the expectations reflected in this news release are reasonable, it can give no assurance such expectations will prove
to be correct. There are a variety of factors which could cause future outcomes to differ materially from those described in this release, including, without limitation, future economic conditions; industry conditions; market conditions; LSB’s capital needs further unexpected delays in readying the Pryor Plant for start-up; and the additional factors referred to under "Special Note Regarding Forward-Looking Statements” contained in LSB’s 2008 Form 10-K and LSB’s Form 10-Qs for
quarterly periods ended March 31, 2009 and June 30, 2009. LSB makes no commitment to disclose any revisions to forward-looking statements, or any facts, events or circumstances after the date hereof that bear upon forward-looking statements.
# # #